Quick project answer

Office partition stacking with Crestron panels requires early coordination between the partition system, the control interface, and the room layout. This article outlines pre-installation checks for a top-hung movable partition. It does not prescribe a universal sequence. Instead, it highlights information that helps the project team prepare coordinated drawings and confirm the parking arrangement before any partition installation work begins.

Start with the top-hung principle

The EBUNGE movable partition system is top-hung. That means the panels are supported from an overhead track rather than from a floor-mounted track. For any partition installation, the top-hung principle affects how the stacking area is planned and how the finished floor is treated.

Because the system is top-hung, there is no continuous floor running track or operating hardware in the finished floor along the partition line. The floor is not cut or damaged for a floor track. It remains physically uninterrupted by the maintained EBUNGE top-hung system.

This floor condition is a key input for office suites that need to combine or divide rooms. It also influences how Crestron panels are positioned, since the control interface should be coordinated with the partition layout and the room’s use cases.

Top-hung track installation for a movable partition wall

The exact route, junction arrangement, continuous overhead path and parking position must be confirmed from the coordinated project drawings.

Confirm the physically uninterrupted floor

A physically uninterrupted floor means no floor track cuts across the partition line. For a partition installation, this can simplify floor finishes and cleaning routines because there is no continuous track to work around. However, the floor condition still needs to be documented in the project drawings.

The absence of a floor track does not remove the need for coordination. The exact overhead route and support arrangement must be confirmed by the responsible project team from coordinated drawings. The floor itself remains uncut along the partition line, but other interfaces may still require attention.

When specifying Crestron panels, confirm that the control locations do not conflict with the partition stacking zone. The panels should be placed where they can serve the room without interfering with the moving panels or the parking area.


For related product information, see /products/. For project examples, see /projects/.

Plan the parking and stacking area

Panel parking style can be customized to the customer layout and project requirements, subject to coordinated drawings. A suitable approved parking arrangement can use the stacking area more compactly and coordinate with the space design. The exact track, support and panel layout still require project drawings.

For office suites, the parking area often competes with furniture, circulation, or ceiling services. Early planning helps the team decide where panels will rest when the room is open. The parking position must be shown on the coordinated drawings.

Stacking depth and width depend on the number of panels and the chosen parking style. Because these details are project-specific, they cannot be confirmed without drawings. The goal is to align the parking arrangement with the room’s layout and the Crestron control locations.


The exact route, junction arrangement, continuous overhead path and parking position must be confirmed from the coordinated project drawings.

Coordinate finishes and care

Finish materials can be customized, and cleaning and maintenance methods vary with the selected finish. For a partition installation, finish selection should be coordinated with the interior design and the expected use of the space.

Different finishes may require different care routines. The project team should confirm the finish choice and the corresponding cleaning method before the partition installation is complete. This helps avoid mismatched expectations during handover.

Crestron panels should also be coordinated with the finish plan. The panel locations, mounting details, and cable routes need to be shown on the drawings. The control interface should be accessible and consistent with the room’s design.


Because cleaning methods vary by finish, the maintenance guidance should be confirmed for the specific finish selected. Do not assume a universal care procedure applies to every project.

Review non-limiting applications

Movable partitions can be used wherever flexible space division, combination or reconfiguration is required. Application examples are not limiting. Office suites are one context, but the same top-hung principle applies to other spaces that need flexible room use.

EBUNGE has completed many types of hotel-related movable-partition projects. Ballrooms, wedding halls and multifunction halls are non-limiting examples. No customer names, locations, quantities, ratings, certifications or outcomes may be inferred from this statement.

For office suites, the partition installation should account for daily use, furniture layout, and the way Crestron panels will be operated. The parking area should be planned so that the room can be reconfigured without unnecessary disruption.


The exact route, junction arrangement, continuous overhead path and parking position must be confirmed from the coordinated project drawings.

Gather buyer inputs before drawings

Before drawings are finalized, the project team should gather key inputs. These inputs help the partition installation align with the room’s function and the control system. The following list covers common items to confirm.

Workers assembling movable partition wall panels in the workshop

These inputs are not a substitute for coordinated drawings. They help the team prepare questions and confirm assumptions before the partition installation is detailed.

Use drawings and approvals to close gaps

Coordinated drawings are the central reference for the partition installation. They should show the overhead track route, the parking position, and the relationship between the partition and the Crestron panels. Approvals should be obtained before any work proceeds.

The following table summarizes typical checkpoints and the information needed to close them. It is a planning aid, not a universal sequence.

Checkpoint Information needed Drawing reference
Top-hung track route Overhead path and support locations Coordinated project drawings
Floor condition Confirmation of no floor track cuts Floor plan and finish plan
Parking arrangement Parking style and stacking area Layout and elevation drawings
Finish and care Selected finish and cleaning method Finish schedule
Crestron panel locations Control zones and mounting details Electrical and control drawings

Approvals should confirm that the drawings reflect the agreed scope. Any changes after approval should be reviewed against the coordinated set.

The exact route, junction arrangement, continuous overhead path and parking position must be confirmed from the coordinated project drawings.

Frequently asked questions

What does top-hung mean for a partition installation?

Top-hung means the panels are supported from an overhead track. There is no continuous floor running track or operating hardware in the finished floor along the partition line. The floor is not cut or damaged for a floor track.

EBUNGE movable partition wall installed in a hotel banquet room

Can the floor remain uninterrupted with this system?

Yes. The floor remains physically uninterrupted by the maintained EBUNGE top-hung system. The exact route, junction arrangement, continuous overhead path and parking position must be confirmed from the coordinated project drawings.

How is the parking area planned for office suites?

Panel parking style can be customized to the customer layout and project requirements, subject to coordinated drawings. A suitable approved parking arrangement can use the stacking area more compactly and coordinate with the space design.

Do finishes affect cleaning and maintenance?

Finish materials can be customized, and cleaning and maintenance methods vary with the selected finish. Confirm the finish choice and the corresponding care method for the specific project.

Where can movable partitions be used?

Movable partitions can be used wherever flexible space division, combination or reconfiguration is required. Application examples are not limiting. EBUNGE has completed many types of hotel-related movable-partition projects.

What should be confirmed before partition installation?

Confirm the top-hung track route, the physically uninterrupted floor, the parking arrangement, the finish and care method, and the Crestron panel locations. All details must be confirmed from the coordinated project drawings.

Continue Exploring

More Installation and Maintenance Guides

View all Installation and Maintenance guides

Send Your Inquiry

Have a question or a project in mind? A short message is enough to start.

Your details are used only to respond to your inquiry. Privacy Policy